Question: jp. You are developing an aggregate plan for a product. At the moment, you are performing calculation for quarter 2 using the chase strategy without
You are developing an aggregate plan for a product. At the moment, you are performing calculation for quarter 2 using the chase strategy without overtime. The quarterly demand must always be satisfied. The forecasted demand is 5891 units. The beginning inventory is 725 units. What is the regular production should be if the ending inventory in quarter 2 must be at least 268 units? The regular production in quarter 2 is units