Question: JT Engineering allocates overhead based on machine hours. The Smelting Department logs 3,200 machine hours and the Polishing Department shows 2,500 machine hours for
JT Engineering allocates overhead based on machine hours. The Smelting Department logs 3,200 machine hours and the Polishing Department shows 2,500 machine hours for the period. If the overhead rate is $4 per machine hour, what should the entry to allocate overhead to production include? $12,800 credit to Work in Process-Assembly and $10,000 debit to Work in Process-Machining $12,800 debit to Work in Process-Assembly and $10,000 credit to Work in Process-Machining $22,800 debit to Manufacturing Overhead $22,800 credit to Manufacturing Overhead