Question: Jun was recently promoted to a Program Manager position. He has set up a Resource Pool file and wants to connect his projects to it.
Jun was recently promoted to a Program Manager position. He has set up a Resource Pool file and wants to connect his projects to it. He connects the file named ConsolidatedPlan A to the resource pool and saves both files. When there is a conflict with regards to resource calendars or resource information, how does Project handle this?
A. The Resource sheet in the sharer file takes precedence.
B. Task assignment information is stored in the sharer files.
C. The information in the Resource Pool file takes precedence.
D. The decision is made on a task by task basis