Question: Jupiter Company applies overhead based on machine hours. The variable overhead standard is 4 hours at $12 per hour. During February, Jupiter Company spent $113,460
Jupiter Company applies overhead based on machine hours. The variable overhead standard is 4 hours at $12 per hour. During February, Jupiter Company spent $113,460 for variable overhead. Assuming 9,150 machine hours were used to produce 2,400 units, how much is variable overhead on the flexible budget?
Multiple Choice
$28,800
$109,800
$113,400
$115,200