Question: Just need answer, will give thumbs up for correct answer! Question 35 (2.5 points) Based on the information below, compute the cost of abnormal spoilage

Question 35 (2.5 points) Based on the information below, compute the cost of abnormal spoilage using the weighted average method for process costing. Assume that costs per equivalent unit under WA are $5 for DM and $7 for CC (The same table is used for Questions 35 and 36.) 2: e 3: Physical units Direct materials Conversion costs Beginning WIP 22 $200 $110 age 4: Started 78 4 Good units completed & transferred out 75 Page 5: 5 Normal spoilage 10 Page 6 Abnormal spoilage 5 Ending WIP 10 Page 7 Total costs added during current month $1,500 $2,000 Degree of completion for BWIP: DM 100%; CC 40% Degree of completion for EWIP: DM 100%; CC 20% a) $120 Ob) $60 c) $80 5: d) $100