Question: Just need question D and also the last question that is not posting. e. use the shortest work element rule to balance the assembly line.
Just need question D and also the last question that is not posting.
Use the longest work element rule to balance the assembly line described in the following table and figure below so that it will produce 48 units per hour. Q D 33 B 66 H 25 20 12 50 16 D 37 a. What is the cycle time? 75 F 62 S unit K 10 5 Work Element should be assigned to Station 2. Work elements G. C should be assigned to Station 3. Work elements D. E. J should be assigned to Station 4. A B D E F G IQ H 1 J K Total Time (sec) 33 66 20 37 12 62 50 25 16 8 10 339 Immediate Predecessor(s) None ABCBEBAHG (Enter your response as a whole number.) b. What is the theoretical minimum number of workstations? 5 stations. (Enter your response rounded up to the next whole number.) c. Using the longest work element rule, which work elements are assigned to each workstation? Work elements A. H. I should be assigned to Station 1. Work element(s) B 1.G D. J. F d. What are the resulting efficiency and balance delay percentages? (Enter your responses as percents rounded to one decimal place.) The efficiency is %. The balance delay is%
e. use the shortest work element rule to balance the assembly line. do you note any changes in solution?

Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
