Question: just the answer i don't need any explanation please 16 - his question is addressing the Risk Knowledge area. Your company has accepted a contract

just the answer i don't need any explanation please

16 -

his question is addressing the Risk Knowledge area.

Your company has accepted a contract to create the operating system for the world's smallest computer. The hardware is being built by University of Michigan, and its function is to collect temperature readings from individual human cells. The idea is that cancer cells are likely at a different temperature than normal human cells, and having this computer take temperature readings on specific cells should help with cutting edge research in the cancer field.

Shortly after your best scrum team starts working on the operating system for this very small computer, your waterfall team comes up with an idea for different kind of operating system, for the same purpose. Instead of shutting down the Scrum Team's efforts, you let them continue, and you plan to use the waterfall team's operating system as a backup plan in case the scrum team fails. By having a solid backup plan ready to go, which kind of method are you using to address risk?

A.

Transference

B.

Avoidance

C.

Acceptance

D.

Mitigation

17 -

In Scrum story points always represent only the duration of a task.

True

False

18-

Please fill in the blank: ___________, do, check, act

Plan

Investigate

prodigitate

elicit

19-

One driving force to the popularity of Agile/Scrum is that change is welcome.

True

False

20-

In Agile/Scrum, a User Story's requirement portion has the format: As a _______, I want ________, so that ________.

True

False

21-

In Agile/Scrum, what is a retrospective?

A.

Cleaning up the product backlog

B.

A time for team members to identify what went right and what could be improved based on the last iteration.

C.

This is when the team commits to doing specific user stories and moves them to the iteration backlog.

D.

A time for the development team to show off its work product to the product owner and clients.

22-

True/False: Pure risk refers to negative risks, not positive risks.

True

False

23-

An activity is a distinct, scheduled portion of work performed during the course of a project.

True

False

24-

A type of contact where the buyer pays the seller a set amount (as defined by the contract), and the seller can earn an additional amount if the seller meets defined performance criteria.

1.

Alternative pricing contracts

2.

Fixed-Price Incentive Fee Contract

3.

Time and materials contract

4.

Fixed Bid

25-

Tom earned his PMP in 2011, and still holds this credential. He was at a meeting where his project was to be discussed with the executives of his company., along with four other projects that he had no involvement in.

While listening to another team present information on their project, called "Project A," he became aware the people working in the financial area of Project A were intentionally making significant ethical violations.

Since Tom is not involved with "Project A," based on PMI's code of ethics, he has no responsibility to report these ethics violations to anyone.

True

False

26-

In the agile manifesto, Individuals and interactions are favored over:

A.

processes and tools

B.

contract negotiation

C.

following a plan

D.

comprehensive documentation

27-

This question is in respect to managing risk.

Your best friend is getting married in St. Louis this weekend! But, you fear the risk of having a flat tire on the way to the ceremony; so you don't go to the wedding. This is an example of:

A.

Avoidance

B.

Transferring

C.

Acceptance

D.

Mitigation

28-

Given: There is only 1 predecessor activity(called "Activity A") to one successor activity (called "Activity "B"). Pictorially; it looks like this:

(Activity A) => (Activity B)

The successor activity ("Activity B") cannot start until its predecessor activity ("Activity A") has finished. Eg. An awards ceremony cant start until after the contest has finished. This relationship is best described as:

A.

Finish to start

B.

start to finish

C.

Start to start

D.

End to End

29-

True/False: Having milestones on your project schedule (time-line) is a great way to let people know whether or not a group of related activities has completed (or started).

True

False

30-

What kind of contract is being referred to here? A type of fixed price contract where the buyer pays the seller a set amount (as defined in the contract), regardless of the sellers costs.

Firm fixed price

retrograde contract

Variable price contract

Fixed-Price Incentive Fee Contracts

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!