Question: K Given the information below, estimate the probability that the noncritical path B-C-G will take more than 15 weeks. Hint Subtract from 1.0 the
K Given the information below, estimate the probability that the noncritical path B-C-G will take more than 15 weeks. Hint Subtract from 1.0 the probability that B-C-G will take 15 weeks or less. Refer to the standard normal table Activity A BCDEFG G Expected Time (weeks) 632694 5055OSO 3.5 6.0 3.5 12.5 6.0 9.5 4.0 Variance 1:25 0.69 0.45 1.78 2.25 2.78 0.49 The probability that this path will take more than 15 weeks to complete is (Enter your response rounded to four decimal places)