Question: KCT4 The eighty-hour rule: Is the time limit to develop the WBS Helps refine major deliverables Makes all WBS tasks two weeks in length Limits

KCT4
The eighty-hour rule: Is the time limit to develop the WBS Helps refine major deliverables Makes all WBS tasks two weeks in length Limits work packages to 80 hours of individual or total team work Helps in the development of the PRD and the project charter The WBS follows a Parent-Child relationship. What is the parent of the work package? The project Major deliverables Control accounts Graphical WBS models The planning process It is the common practice in an organization to copy a WBS from a previous project. What should be done to a copied WBS to make it useable? Execute carefully ensuring work packages are accomplished Attach it to the project charter Tailor the WBS to reflect the current project Use to solicit request for proposals Share with all team members