Question: Kimberly a project manager and a software development company is assigned a new project shes given a budget of $500,000 and a span of six

Kimberly a project manager and a software development company is assigned a new project shes given a budget of $500,000 and a span of six months to complete the project in three months she is able to complete 60% of the project in the scenario to earn value of the work completed is

250,000

300,000

350,000

150,000

200,000