Question: Kimberly a project manager and a software development company is assigned a new project shes given a budget of $500,000 and a span of six
Kimberly a project manager and a software development company is assigned a new project shes given a budget of $500,000 and a span of six months to complete the project in three months she is able to complete 60% of the project in the scenario to earn value of the work completed is
250,000
300,000
350,000
150,000
200,000
Step by Step Solution
There are 3 Steps involved in it