Question: Kimberly is the project manager on a five-year construction project now in Year 3. During Years 1-2 the project ran behind schedule due to severe
Kimberly is the project manager on a five-year construction project now in Year 3. During Years 1-2 the project ran behind schedule due to severe weather. Kimberley is reviewing work performance data from the first quarter of Year 3. Using trend analysis,she will learn if