Question: Kindly answer all 6 questions please. ( shown in the photo attached ) They are all connected. Thank you very much. average angle of swing

Kindly answer all 6 questions please. (shown in the photo attached) They are all connected. Thank you very much.
average angle of swing is 90.
Using information from the previous question, what would be the dimensions of a
triangular spoil bank if the trench is 2000 yards long and the cross section of the
trench is as seen below?
A hydraulic shovel with a 2.3 yd.?3 front dump bucket will load the sand and
gravel from the previous question into haul units for removal. The average angle
of swing is 75 and job efficiency is the same as in question 1. What is the
expected production in LCY/hour?
Calculate the number of haul units theoretically required in the previous question
if the unit haul capacity is 15LCY and truck cycle time excluding loading is 30
minutes.
What is the total cost of the project based on the hourly charge for operator &
equipment based on the volumes calculated and the production of each piece of
equipment?
a. Excavator and operator $100 per hour
b. Loader and operator $100 per hour
c. Each Haul unit $70 per hour
What is the unit cost per LCY?
Kindly answer all 6 questions please. ( shown in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!