Question: KINDLY ANSWER AS SOON AS POSSIBLE 5) There are six jobs to be processed on three machines A, B and C in the order CAB.

KINDLY ANSWER AS SOON AS POSSIBLE
5) There are six jobs to be processed on three machines A, B and C in the order CAB. The following table indicates the processing time in hours for the six jobs on the three machines. Obtain optimum sequence of jobs that minimizes the total elapsed time for completing all the jobs on the three machines. Also indicate the idle time of each machine. (5) Jobs 1 2 3 4 5 6 3 5 6 Processing time in hours on M/A 4 6 7 5 3 Processing time in hours on M/c B 8 107 8 11 8 Processing time in hours on M/c C 5 6 2 3 49 4 toomStep by Step Solution