Question: King Builders gets a CIP for a $200 million construction program involving work in 12 states. Construction is expected to last two years. Which of
King Builders gets a CIP for a $200 million construction program involving work in 12 states. Construction is expected to last two years. Which of the following suggests that the construction program is NOT well suited to a CIP? o a. The construction operations are very spread out. Ob. The project is not large enough for a CIP. Oc. The project is too large for a CIP. Od. The project time frame is too long for a CIP