Question: KPNG Consulting has five projects to consider. Each will require time in the next four quarters according to the table below Project Time in 1st
KPNG Consulting has five projects to consider. Each will require time in the next four quarters according to the table below
| Project | Time in 1st quarter | Time in 2nd quarter | Time in 3rd quarter | Time in 4th quarter | Revenue $k |
| A | 6 | 9 | 3 | 1 | 240 |
| B | 4 | 13 | 6 | 4 | 120 |
| C | 8 | 0 | 8 | 6 | 150 |
| D | 3 | 3 | 1 | 7 | 60 |
| E | 12 | 3 | 4 | 9 | 250 |
Revenue from each project is also shown. Develop a model whose solution would maximize revenue, meet the time budget of: 28 in the 1st quarter, 20 in the 2nd quarter, 18 in the 3rd quarter and 16 in the 4th quarter; at least three projects; and not do both projects C and D. If project B is chosen, project D must be chosen.
Step by Step Solution
There are 3 Steps involved in it