Question: lA project has three tasks: A , B and C . Task A takes 3 days, B takes 5 and C takes 7 . A

lA project has three tasks: A, B and C. Task A takes 3 days, B takes 5 and C takes 7. A is the precedent to C. The total budget allots A and B costs of $200 per day of work each, and C $150 per day.
5 days of work have been completed on time, except C is one day behind schedule. The project manager has spent $1600 so far.
What is the:
schedule ratio?
[ Select ]
cost ratio?
[ Select ]
critical ratio?
[ Select ]
The project manager should
[ Select ]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!