Question: lA project has three tasks: A , B and C . Task A takes 3 days, B takes 5 and C takes 7 . A
lA project has three tasks: A B and C Task A takes days, B takes and C takes A is the precedent to C The total budget allots A and B costs of $ per day of work each, and C $ per day.
days of work have been completed on time, except C is one day behind schedule. The project manager has spent $ so far.
What is the:
schedule ratio?
Select
cost ratio?
Select
critical ratio?
Select
The project manager should
Select