Question: Lab Project # 3 ( 1 5 pts . ) IS 1 8 7 / MGMT 1 5 8 S 2 0 2 0 Time
Lab Project # pts
IS MGMT S
Time Management
The time management knowledge area is one of the most important chapters in the
PMBOK Guide from a PMP exam point of view.
You are going to see a lot of questions from this chapter in the exam; therefore study
this chapter thoroughly and make sure you are able to solve all practice questions given
in this chapter.
In the exam you can see questions from following given topics:
Triangular Distribution
Beta Distribution PERT
Standard Deviation, Variance
Critical Path Method
Type of Dependency
Total Float and Free Float
Schedule Compressions Technique
Crashing
Now lets discuss each of them in detail.
Triangular and beta distribution are used to calculate the activity duration. To calculate
triangular or beta estimate you use three estimates for each activity:
Optimistic Estimate
Pessimistic Estimate
Most Likely Estimate
The optimistic estimate is the least possible time in which the activity can be finished. It
is denoted by to
The pessimistic estimate is the worst case scenario. Here you assume the worst case for
the activity to complete. Simply put, this is the maximum time required to complete an
activity. It is denoted by tp
The most likely estimate is the most probable time the activity will take to be completed.
It is denoted by tm
Once you get these three estimate, you can calculate the triangular or beta estimate very
easily.
Triangular Distribution
In triangular distribution, the mean is equal to the sum of these three, and divided by
three. Mean Optimistic Mostlikely Pessimist
Or
Expected Duration Triangular Distribution teto tm tp
Example
Your team member told you that in your project, painting work may take days to
complete. However, if the weather is not favorable it will take days. He also told you
that if all conditions are good, painting can be completed in days.
Using triangular distribution, calculate the expected duration for this activity.
Solution:
According to triangular
estimate, Expected
Duration teto tm
tp Given Data:
tm days tp days to days
Therefore, expected duration
days
Practice Question:
You have been given a task which might take days to complete; however if the conditions
are favorable it might be completed in days. In the worst case scenario, it may take
days.
Find the average estimate for this task using triangular estimate.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
