Question: Labor Planning Labor Information Regular Rate $ 1 7 . 0 0 / hr Overtime Rate $ 2 2 . 5 0 / hr Targeted

Labor Planning
Labor Information
Regular Rate $17.00/hr
Overtime Rate $22.50/hr
Targeted Labor Cost $11,050/wk
Labor Hours Needed 650/wk
Any hour worked over 40 hrs/wk must be paid overtime rate
17
29
277
492
650
How many workers are needed to meet the targeted labor cost?Required question.