Question: Labour information Standard rate 1 5 . 0 0 / hr Overtime rate 2 4 . 5 0 / hr Targeted labour cost 1 2

Labour information
Standard rate 15.00/hr
Overtime rate 24.50/hr
Targeted labour cost 12,000/wk
Labour hours needed 800/wk
Any hour worked over 40 hrs/wk must be paid at the overtime rate
For 13 person team , how does the actual weekly labours cost compare to the target ?
27
67
320
1,000
7,840