Question: lag question: Question 12 Question 121 pts When must the ends of projecting reinforcing steel be protected by caps of covers? Group of answer choices
lag question: Question 12
Question 121 pts
When must the ends of projecting reinforcing steel be protected by caps of covers?
Group of answer choices
when the rebar is No. 4 or smaller;
if the rebar is to be exposed for more than 48 hours
when the rebar extend more than 24 inches
When the location is high enough that a worker can be impaled upon it
Flag question: Question 13
Question 131 pts
A construction firm has an annual estimated fixed overhead cost of $ 500,000.00. During the year, the actual overhead was $ 550,000.00. The forms' gross billings for the year were $ 6,000,000.00. Each of the jobs had been estimated with a 10% allowance for overhead and profit. Assume that all jobs were accurately managed. What was the firm's actual profit?
Group of answer choices
$ 50,000
$ 450,000
$ 105,000
$ 100,000
Flag question: Question 14
Question 141 pts
What is the actual nominal size of a number 8 rebar?
Group of answer choices
1 foot
7/8 inch
1 inch
inch
Flag question: Question 15
Question 151 pts
What is the distance for the upper surface of a guardrail above the walking/working surface?
Group of answer choices
45 - 48 inches
38-42 inches
36-39 inches
36-45 inches
Flag question: Question 16
Question 161 pts
A tandem dump truck has a purchase price of $ 80,000.00 and a usable life of 10 years. At the end of the usable life it has no salvage value. What is the annual depreciation on this vehicle in year 12? $ 0; $ 80,000; $ 8,000;
Group of answer choices
$ 80000
0
$ 96,000
$8000
Flag question: Question 17
Question 171 pts
In the estimating process, a contractor normally adds a markup or margin. This is an allowance for
Group of answer choices
Liquidated damages
Contingency
general overhead
profit
Flag question: Question 18
Question 181 pts
All of the following are examples of indirect costs except
Group of answer choices
equipment rentals for the project
payroll taxes
workers compensation insurance
corporate income taxes
Flag question: Question 19
Question 191 pts
Which of the following bonds is always required on a construction project?
Group of answer choices
performance bond
bid bond
payment bond
maintenance bond
Flag question: Question 20
Question 201 pts
The amount of money deducted by the owner from a progress payment is called
Group of answer choices
hold back
liquidated damages
retainage
recovery charges
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
