Question: Lake Lee has a phosphorus total maximum daily load ( TMDL ) established at 6 5 6 . 0 3 k g y r .

Lake Lee has a phosphorus total maximum daily load (TMDL) established at 656.03kgyr. The only known point source, a local wastewater treatment
plant, is permitted to discharge 0.68lbm? day of phosphorus into Lake Lee. The total phosphorus (TP) loading from the farmland within the Lake Lee
watershed is estimated at 253.85kgyr. The associated established margin of safety is 10%. To meet Lake Lee's phosphorus TMDL, the additional
allowable TP load allocation within the Lake Lee watershed is most nearly
A.220kgyr
B.260kgyr
C.340kgyr
D.480kgyr