Question: ** last person to answer this, totally gave the wrong answer to a different problem, trying this again please Jack has gathered the following information

** last person to answer this, totally gave the wrong answer to a different problem, trying this again please

Jack has gathered the following information for Work Center 2, the work center that directly feeds Work Center 3. Complete the input/output analysis of Work Center 2.

Input Information (in hours)

4

5

6

7

8

Planned input

55

65

65

75

75

Actual input

25

35

35

40

40

Output Information (in hours)

4

5

6

7

8

Planned output

40

65

65

75

75

Actual output

45

45

45

55

75

Backlog105hours

Jack has asked you to calculate the following for Work Center 2.

(a)

New attempt is in progress. Some of the new entries may impact the last attempt grading.

Your answer is incorrect.

Calculate the percentage of planned output needed to complete the planned inputs [(planned input + backlog)/ planned output] at Work Center 2. (Round your answers to 1 decimal place, e.g. 17.5.)

4

5

6

7

8

Percentage of planned output

100%

enter percentages %

enter percentages %

enter percentages %

enter percentages %

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!