Question: Last Saved: 10:05 PM 3) The project control process should (5pts) o be performed on a regular basis O provide status updates identify issues and

Last Saved: 10:05 PM 3) The project control process should (5pts) o be performed on a regular basis O provide status updates identify issues and concerns bandc All of the above 4) To determine whether your project is under or over budget, you should evaluate (5pts) ACWP- BCWP BCWP - BCWS BCWS - BCWP ACWP/BCWP Last Saved: 10:05 PM 3) The project control process should (5pts) o be performed on a regular basis O provide status updates identify issues and concerns bandc All of the above 4) To determine whether your project is under or over budget, you should evaluate (5pts) ACWP- BCWP BCWP - BCWS BCWS - BCWP ACWP/BCWP