Question: Last year I did a project. One activity was pouring a concrete pad. It took 1 0 hours. This year I have a similar project

Last year I did a project. One activity was pouring a concrete pad. It took 10 hours. This year I have a similar project to pour a concrete pad that is 20% larger. Some experts say that since I did it last year, this year I can do better and get it done 20 percent faster than last year. Other experts say this year the labour is not as good and so I will get it done in 30% longer. How long should my duration be?[8].