Question: lead time demand for pc jump drives avergaes 50 units (normally distrubuted), with a standard deviation of 4 drives. management wants a 90% service level.
lead time demand for pc jump drives avergaes 50 units (normally distrubuted), with a standard deviation of 4 drives. management wants a 90% service level.
what safety level do you recommend?
what is the appropriate reorder point?