Question: Lead time for cakes is 2 days with daily demand of 4 cakes and a safety stock of 1/2 day. Each container (kanban) holds 2
Lead time for cakes is 2 days with daily demand of 4 cakes and a safety stock of 1/2 day. Each container (kanban) holds 2 cakes. What is the correct number of kanbans? 10 O1 5
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
