Question: Lead time is when: Question 2 options: you purposefully put a delay between the predecessor task and the successor activities finish at the same time

Lead time is when:
Question 2 options:
you purposefully put a delay between the predecessor task and the successor
activities finish at the same time
you give a successor task some time to get started before the predecessor finishes.
you need to coordinate activities so they begin at the same time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!