Question: Lead times for item A and its components are given in the table below: Item A B C D E F Lead Time 1 week
Lead times for item A and its components are given in the table below:
| Item | A | B | C | D | E | F |
| Lead Time | 1 week | 2 weeks | 3 weeks | 4 weeks | 5 weeks | 6 weeks |
Using the lead time information given above, develop the gross material requirements plan with a production schedule that will satisfy the demand of 100 units of item A by week 8 (as shown in the table below. Please note that you are asked to develop the gross material requirements plan with Required date and Order release date for items A, B, C, and D only. In the table below, A, B, C, and D represent items A, B, C, and D, respectively:
| Week | ||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
| A. Required date | 100 | |||||||
| Order release date | ||||||||
| B. Required Date | ||||||||
| Order release date | ||||||||
| C. Required date | ||||||||
| Order release date | ||||||||
| D. Required date | ||||||||
| Order release date | ||||||||
Please complete the table
B = 2A C = 3A D = 1B +2C E = 3B F =3C
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
