Question: Lead-time demand for a product is normally distributed with an average of 100 units and a standard deviation of 25 units. If the company wants
Lead-time demand for a product is normally distributed with an average of 100 units and a standard deviation of 25 units. If the company wants to maintain a 90% service level, how many units should be carried as safety stock?