Question: Learning Curve Sharon Glessing, controller for Janson Company, has noticed that the company faces a 70 percent learning rate for its specialty design line. In

Learning Curve

Sharon Glessing, controller for Janson Company, has noticed that the company faces a 70 percent learning rate for its specialty design line. In planning the cost of the latest design, Sharon assumed that the first set of units would take 1,000 direct labor hours. She decided to use this information in budgeting for the cost of the total project, which would involve the manufacture of 16 sets. Direct labor is paid $40 per hour.

Required:

1. Complete the table below showing results by row for total production of: one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) (Round Cumulative Total Time answers to the nearest whole number.)

Cumulative Number of Units Cumulative Average Time per Unit in Hours Cumulative Total Time: Labor Hours
1 fill in the blank 1 fill in the blank 2
2 fill in the blank 3 fill in the blank 4
4 fill in the blank 5 fill in the blank 6
8 fill in the blank 7 fill in the blank 8
16 fill in the blank 9 fill in the blank 10

2. What is the total labor cost if Janson Company makes eight sets? Sixteen sets? (Use the rounded answers in the subsequent computations).

Total labor cost for eight sets $fill in the blank 11
Total labor cost for sixteen sets $fill in the blank 12

3. Using the logarithmic function, complete the table below showing results by row for each of unit sets one through eight. (Round hour answers to two significant digits.) (Round Cumulative Total Time and Time for Last Unit answers to the nearest whole number.)

Cumulative Number of Units Cumulative Average Time per Unit in Hours Cumulative Total Time: Labor Hours Time for Last Unit
1 fill in the blank 13 fill in the blank 14 fill in the blank 15
2 fill in the blank 16 fill in the blank 17 fill in the blank 18
3 fill in the blank 19 fill in the blank 20 fill in the blank 21
4 fill in the blank 22 fill in the blank 23 fill in the blank 24
5 fill in the blank 25 fill in the blank 26 fill in the blank 27
6 fill in the blank 28 fill in the blank 29 fill in the blank 30
7 fill in the blank 31 fill in the blank 32 fill in the blank 33
8 fill in the blank 34 fill in the blank 35 fill in the blank 36

What is the direct labor cost for the eighth set?

$fill in the blank 37

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!