Question: LeBron Corp. signed a fixed-price $6,500,000 contract to construct a building. At the end of Year 1, LeBron had incurred $1,000,000 in total costs, and

LeBron Corp. signed a fixed-price $6,500,000 contract to construct a building. At the end of Year 1, LeBron had incurred $1,000,000 in total costs, and expected to incur $3,500,000 in additional costs to complete the building. By the end of Year 2, LeBron had incurred total-costs-to-date of $3,000,000 and expected to incur $1,500,000 in cost to complete the building. How much profit should LeBron recognize in Year 2 under the percentage of completion method?