Question: Lecture 2 : Prints for Construction Phases Class Activity 0 1 - The conception phase One of the first decision of any building construction projects

Lecture 2: Prints for Construction Phases
Class Activity 01- The conception phase
One of the first decision of any building construction projects is to locate the building. Among the factors contributing to this decision is the amount of cut and fill (total excavation). Ideally cut and fill should be balanced.
For the following example, first divide the entire building's pad into four equal regions. Second, add an approximate existing elevation to each corner of the regions (note: use an average for the corners fall between two contour lines).
Last, fill the following table and calculate the cut and fill volumes.
\table[[Region Avg.,Cut (-) or,Cut (-) or,],[,Elv.,Fill (+) Depth,Fill (+) Vol.]]
A1
A2
A3
A4
Total Cut Volume (cu. ft.)=
Total Fill Volume (cu. ft.)=
Net Cut/Fill (cu. ft.)=
Show the cut and fill area on the example.
Lecture 2: Prints for Construction Phases
Locate the building to achieve less than 50cu.ft. net cut/fill and show the cut and fill area.
Lecture 2 : Prints for Construction Phases Class

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!