Question: LEGEND EARLY START DURATION EARLY FINISH TASK NAME 7 LATE START SLACK LATE FINISH D 0 3 5 A G 10 10 5 C E

LEGEND EARLY START DURATION EARLY FINISH TASK

LEGEND EARLY START DURATION EARLY FINISH TASK NAME 7 LATE START SLACK LATE FINISH D 0 3 5 A G 10 10 5 C E 1 0 N B 20 H 5 F Based on the network diagram above, what is the early start of activity H? You will need to calculate all ES, EF, LS, LF, slack and critical path information to answer the five questions pertaining to this diagram