Question: Lens are assembled in a two-step process with two sequential resources. The capacities of the resources are 1.1 and 0.8 lens per hour. How long
Lens are assembled in a two-step process with two sequential resources. The capacities of the resources are 1.1 and 0.8 lens per hour. How long does it take 14 lines to be assembled in hours?