Question: Let job set J={J 1 , J 2 , J 3, J 4 }, J i =(r i , c i , d i ),
Let job set J={J1, J2, J3, J4}, Ji=(ri, ci, di), where ri , ci, and di are the arrival time, the worst case execution cycles, and deadline for Ji, respectively. Let J1=(1, 3, 16), J2=(4, 4, 24), J3=(12, 5, 22), J4=(0, 2, 40) be scheduled on an ideal DVS processor according to EDF. Find the voltage schedule that can minimize the dynamic energy consumption to complete these jobs in time.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
