Question: Let's cost a job. Here is some data. What is the total cost on this job? Direct Materials $2,245 Direct Labor hours incurred to complete
Let's cost a job. Here is some data. What is the total cost on this job?
| Direct Materials | $2,245 |
| Direct Labor hours incurred to complete job | 142 hours |
| Hourly wage rate for DL workers | $25.00 |
| Predetermined Overhead Rate | $82 per DL hour |