Question: Level Loading problem with schedule building: Please try to level load the following problem and tell me what the results are. Problem 1: Please make
Level Loading problem with schedule building:
Please try to level load the following problem and tell me what the results are.
Problem 1:
Please make sure that you have the staffing you need and adjust the schedule to fit your staffing. I would like our schedule not to be compressed, causing overtime and work over the weekend.
You have 2 computers (C ), 2 analysts (A), and 2 programmers (P ) for this project.
| Task | Duration | Predecessor | Needs |
| A | 3 | none | 1 C, 2 A, 2 P |
| B | 2 | none | 1 C, 1 A, 1 P |
| C | 2 | B | 1 C, 1 A, 1 P |
| D | 3 | A | 2 C, 2 A, 2 P |
| E | 2 | D, C | 2 C, 2 A, 2 P |
| F | 1 | E | 2 C, 2 A, 2 P |
- First you have to build the schedule given the information above.
- What is your critical path?
- Can float or slack help you at all?
- Draw a GANNT chart, including your aggregated resources at the bottom of the chart. Show how you needed to move tasks to fit within your resource constraints.
Problem 2:
Here is an idea for completing the project above. Try this variation once you have completed the Problem 1. What if we don't Use any computer staffing on A or D, and speed up E by having C be the only predecessor to E? We would be taking on some risk, but could we get the project done on time then?
- Again, build the schedule given the information above.
- What is your critical path?
- Can float or slack help you at all?
- Draw a GANNT chart, including your aggregated resources at the bottom of the chart. Show how you needed to move tasks to fit within your resource constraints.