Question: Leveling data is collected with a Leica Sprinter 2 5 0 M digital level and aluminum rod. The instrument spec sheet from Leica states, with

Leveling data is collected with a Leica Sprinter 250 M digital level and aluminum rod. The instrument spec sheet from Leica states, with this system, the expected random error in each measurement is 1 mm 1. If you run a level loop with 1212 measurements, how would you predict the expected random error to the nearest 0.01 mm?