Question: Levelling resource needs within a project refers to Question 26 options: Eliminating resources requests that exceed a certain limit Adjusting the scheduling of work packages
Levelling resource needs within a project refers to
Question 26 options:
|
| Eliminating resources requests that exceed a certain limit |
|
| Adjusting the scheduling of work packages to minimize the maximum resource requirement |
|
| Acquiring additional resources to handle peak demand of the project |
|
| Being honest with management about the total extent of resource requirements, particularly if the requirement is over budget |
|
| Asking for additional budget to handle peak resource demand |
As a project nears completion, the total risk of the project will most likely
Question 6 options:
|
| Increase |
|
| Decrease |
|
| Remain the same |
Sometimes when crashing a project to reduce overall project duration by one unit of time (for example, a single day), we find that we have to crash more than one activity because there is more than one critical path in the AON.
Question 15 options:
| True | |
| False |