Question: life = 7 y r . The machine is planned for a two - shift operation, 8 hours per shift, 5 days per week, 5
life The machine is planned for a twoshift operation, hours per shift, days per week, weeks per year. The applicable overhead rate on this type of equipment Determine the equipment cost rate.
The production machine in is used to sequentially produce a batch of parts that each has a starting cost of $ Batch quantity The actual processing time in the operation min. Time to load and unload each workpiece min. Tool cost $ and each tool can be used for pieces before it is changed, which takes hours. Hourly wage rate of the operator $ and the applicable labor overhead rate Determine a the cycle time for the piece, b average production rate when setup time is figured in and c cost per piece.