Question: LightEdge Technologies would like to put in place an assembly line in its Mexican facility that puts together Internet servers. The tasks needed to accomplish

LightEdge Technologies would like to put in place an assembly line in its Mexican facility that puts together Internet servers. The tasks needed to accomplish this, including times and predecessor relationships, are as follows:
\table[[TASK,TIME (MINUTES),IMMEDIATE PREDECESSOR],[A,2.9,None],[B,0.2,None],[C,0.25,A, B],[D,0.4,A, B],[E,1.7,C],[F,0.1,C, D],[G,0.7,D],[H,1.7,E, F, G],[I,1.2,H],[J,2.3,I],[K,2.7,I],[L,1.5,J, K]]
a.(**) Draw a precedence diagram for the tasks. Suppose the takt time is 240 seconds (four minutes). What is the theoretical minimum number of workstations?
 LightEdge Technologies would like to put in place an assembly line

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!