Question: Like in the previous question, the values in the boxes show the task names and their duration. Now the pair of numbers above each box

Like in the previous question, the values in the

Like in the previous question, the values in the boxes show the task names and their duration. Now the pair of numbers above each box show the latest start time and latest finish time (LST and LFT) for that task, respectively. So for example, task U has LST=5 and LFT=8. fe dc 5 8 P:2 Q:3 R:3 i 8 Start End h 8 ba 5 8 S:3 T:1 U:3 In this question, we will practice a backward path calculation. Therefore calculate the unknown LST and LFT values, a,b,c,d,e,f,g,i