Question: likely, b = pessimistic times ) . Assume that the activity times are independent: Time Activity Immediate predecessor ( s ) a m b A

likely, b= pessimistic times). Assume that the activity times are independent:
Time
Activity
Immediate predecessor(s)
a
m
b
A
-
11
15
19
B
-
27
31
41
C
-
18
18
18
D
A,B
9
10
11
E
C
5
8
11
F
D,E
16
19
22
a) Determine the total expected project completion time.
b) What is the critical path of the project?
Select one:
a)59 weeks; b) A-D-F
a)61 weeks; b) B-D-F
a)61 weeks; b) A-B-D-F
a)42 weeks; b) C-E-F