Question: likely, b = pessimistic times ) . Assume that the activity times are independent: Time Activity Immediate predecessor ( s ) a m b A
likely, b pessimistic times Assume that the activity times are independent:
Time
Activity
Immediate predecessors
a
m
b
A
B
C
D
AB
E
C
F
DE
a Determine the total expected project completion time.
b What is the critical path of the project?
Select one:
a weeks; b ADF
a weeks; b BDF
a weeks; b ABDF
a weeks; b CEF
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
