Question: Linear Programming Exercise TRUE & FALSE 1. Let P be the shortest path from some node s to some other node t in a graph.

Linear Programming Exercise

TRUE & FALSE

1. Let P be the shortest path from some node s to some other node t in a graph. If the weight of each arc in the graph is doubled, P will remain as the shortest path from s to t. T/F

2. In an Activity-On-Node graph of project management, if the arc from activity 3 to activity 5 is not on the critical path, then the shadow price of constraint

t_5 - t_3 >= d_3 where d_3 is the current duration of activity 3, is 0. T/F

3. Suppose you have a project you want to expedite. There are expediting costs for each day of each activity. There is a penalty of $30 for each day the project extends beyond 10 days and there is a reward of $40 for every day the project finishes under 10 days. You want to minimize the total cost. Can you solve this problem with a single LP?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!