Question: Linear programming model problem Carlsons is a bushes manufacturing company and produces three types of bushes used in washing machines. An operations manager is trying

Linear programming model problem

Carlsons is a bushes manufacturing company and produces three types of bushes used in washing machines. An operations manager is trying to determine a production plan for the next week. The types of the bushes are named as small, medium and large bushes and they have a limitation on their manufacturing quantities. Small bushes have a limit of 100, medium 40 and a limit of 60 for Large bushes. The remaining data required for this problem are enumerated in the tables Table 1 and Table 2 and are arranged with respect to machine processing requirements. Table 1 contains the availability of the machines and the number of units being produced. Table 2 contains the product data like revenue per unit and the cost of product per unit.

Table 1

Machine

Unit processing time (minutes)

Availability (minutes)

Small

Medium

Large

1

20

10

10

2400

2

12

28

16

2400

3

15

6

16

2400

4

10

15

0

2400

Table 2.

Item

Small

Medium

Large

Revenue per unit

$90

$100

$70

Cost per unit

$45

$40

$20

  1. Formulate a Linear programming model for this problem (15 points).
  2. What is the optimal solution? Solve using excel (15 points).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!