Question: Linking a part requirement with the parent component that caused the requirement is referred to as a) economic lot sizing Ob) Kanban c) Leveling d)

Linking a part requirement with the parent
Linking a part requirement with the parent component that caused the requirement is referred to as a) economic lot sizing Ob) Kanban c) Leveling d) net requirements planning e) pegging