Question: List ES , EF , LS , LF , and Slack for all activities on the network and identify the critical path and completion time.

List ES, EF, LS, LF, and Slack for all activities on the network and identify the critical path and
completion time. (6pt)
b. For the indirect cost, if the project can be finished in 26 days, it is $4500; if the project can be
finished in 25 days, it is $4200; if the project can be finished in 24 days, it is $3900; if the project
can be finished in 23 days, it is $3600; if the project can be finished in 22 days, it is $3200; if the
project can be finished in 21 days, it is $2700