Question: - llange 0 0 : 0 1 CCB 5 4 2 Assignment 2 ( 1 ) . pdf QUESTION A contract for an office building

-llange
00:01
CCB 542 Assignment 2(1).pdf
QUESTION
A contract for an office building includes the provision of a storage tank. Drawing No. QI shows the plan and section of the proposed storage tank. Take off quantities for the following work.
a. Topsoil excavation.
(5 Marks)
b. Basement excavation.
(9 Marks)
c. Filling to basement excavation and replacement of topsoil around the structure.
(11 Marks)
Specifications
Topsoil to be excavated over the area of the structure for a width of 4m all round same and deposited 15m away for re-use.
Topsoil to be excavated to a depth of 150mm.
Excavate for basement including filling around the structure and remove surplus soil from site.
Filling is to be of selected excavated material.
Filling around the structure with topsoil 150mm depth.
2
- llange 0 0 : 0 1 CCB 5 4 2 Assignment 2 ( 1 ) .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!