Question: Loans are evaluated in a process with two resources. A worker in the first resource evaluates 3.6 loans per hour and a worker in the

Loans are evaluated in a process with two
Loans are evaluated in a process with two resources. A worker in the first resource evaluates 3.6 loans per hour and a worker in the second resource evaluates 3 loans per hour. The first resource has 5 workers and the second resource has 8 workers. Demand occurs at the rate 21 loans per hour. Instruction: Round your answer to 1 decimal place. What is the utilization (%) of the second resource