Question: Looking at the burndown chart below, assume each dot is a day in the sprint. Looking at day 2, is the team behind or ahead
Looking at the burndown chart below, assume each dot is a day in the sprint. Looking at day 2, is the team behind or ahead of the planned story point burndown? Question 14 options: Right on track Behind Ahead